Visayas Grid Alert: Why Cebu's Power Supply Is Tight This Christmas

NGCP placed the Visayas grid on yellow alert again on November 26 after a red alert earlier in the week. Here's what is behind the thin supply and what Cebu households can do.

Cebu
Cebu City skyline with high-rise buildings under a clear sky
Photo: DisRaptor18 / CC0, via Wikimedia Commons
In this article
  1. What the Visayas grid alert on November 26 means
  2. Red alert earlier in the week
  3. Why Cebu is especially exposed
  4. When relief is expected
  5. What Cebu households and businesses can do
  6. Sources

Another Visayas grid alert was raised on Thursday, November 26, 2026, when the National Grid Corporation of the Philippines (NGCP) put the Visayas grid on yellow alert from 4 p.m. to 7 p.m. It was the latest in a string of yellow and red alerts this month, including a one-hour red alert on Monday, November 23. Cebu has so far avoided rotational brownouts, but only because extra power was sent in from Mindanao and Luzon.

What the Visayas grid alert on November 26 means

According to an NGCP advisory reported by DZRH, available capacity on the Visayas grid on November 26 was 2,567 megawatts (MW), while peak demand was expected to reach as much as 2,480 MW. That leaves a thin cushion. NGCP issues a yellow alert when the operating margin is not enough to cover the grid's contingency requirement, meaning that one more plant tripping could push the system into trouble.

NGCP linked the tight margin to several problems at once:

  • an unplanned outage of Therma Visayas Inc. (TVI) Unit 2 and reduced output from TVI Unit 1;
  • planned maintenance outages at Palm Concepcion Power Corp. and KSPC Unit 2;
  • limited power imports from the Mindanao grid.

DZRH reported that 24 plants were on forced outage, some of them since as far back as 2021, and 18 more were running below full capacity. In total, about 616 MW could not be used by the grid.

Red alert earlier in the week

Philstar.com reported that on Monday, November 23, NGCP placed the grid on yellow alert from 3 p.m. to 5 p.m. and again from 6 p.m. to 8 p.m., with a red alert in between, from 5 p.m. to 6 p.m. At that time 612.5 MW was unavailable, with 21 plants on forced outage and 21 others derated. Imports from Mindanao were limited because some Mindanao units were themselves on planned outage.

The difference between the two levels matters. A yellow alert warns that reserves may not be enough if something else breaks down. A red alert means supply is not enough to meet demand, which is when grid operators may resort to rotational load shedding.

Why Cebu is especially exposed

Cebu is the biggest demand centre in the Visayas, and it relies heavily on power brought in from other islands. In a meeting with power officials reported by The Freeman on November 26, Cebu City Mayor Nestor Archival heard that Cebu's demand is about 1,400 MW, while local generation had dropped to around 700 MW because of outages and reduced output at several plants.

The gap was covered this month when Mindanao delivered its full 450 MW allocation and Luzon sent another 250 MW, The Freeman reported. Visayan Electric president and general manager Mark Anthony Kindica said the distribution utility had not carried out any rotational brownouts in November up to the meeting.

There is also a structural bottleneck. The Freeman noted that the Luzon-Leyte interconnection, built in 1997, limits how much power can flow from Luzon to the Visayas. Mayor Archival said short-term fixes would not end the recurring problems and asked power stakeholders for clear target dates on long-term projects, warning that hot El Niño conditions could push demand even higher.

When relief is expected

Officials gave The Freeman these expected dates:

Plant or projectStatus reported
TVI Unit 2, Toledo City (169 MW)Expected back by December 2
KEPCO-SPC plant, Naga CityMaintenance to finish by early December
A facility in PanayMaintenance to finish by early December
New planned outages in DecemberNot allowed during the holidays
NGCP Luzon-Leyte-northern Cebu transmission backboneTargeted for 2031
"Airbag Project" battery storage (up to 750 MW across the Visayas)Mayor asked NGCP to roll out parts sooner

Plant return dates can slip, so watch NGCP and Visayan Electric advisories for the latest grid status.

What Cebu households and businesses can do

Officials at the meeting urged consumers to cut electricity use during the late-afternoon and evening peak, which is exactly when the recent alerts were in effect. Practical steps include:

  1. Set air-conditioners a few degrees warmer, or switch to fans during peak hours.
  2. Move energy-heavy chores such as laundry, ironing and water heating to daytime.
  3. Keep phones and power banks charged before 4 p.m. in case of interruptions.
  4. Businesses with their own generators can ask Visayan Electric about its expanded Interruptible Load Program, which lets them switch to self-generated power when reserves get critical.

If you are visiting Cebu over the holidays, most hotels and malls run backup generators, but it still pays to keep a charged power bank and check the Cebu and Davao weather page for heat conditions. For a wider look at the island, see our Cebu guide, and follow the latest updates on our news page.

Sources

Frequently Asked Questions

What is the difference between a yellow and a red alert on the Visayas grid?

A yellow alert means the grid's reserves may not be enough if another plant fails. A red alert means available supply cannot meet demand, which can lead to rotational brownouts.

Has Cebu had rotational brownouts in November 2026?

Visayan Electric said it had not implemented rotational brownouts in November up to its meeting with Cebu City officials, thanks to extra power imported from Mindanao and Luzon.

When will the Visayas power supply improve?

Officials expect TVI Unit 2 in Toledo City back by December 2 and other plants in Naga and Panay to finish maintenance by early December. A major transmission upgrade from Luzon to northern Cebu is targeted for 2031.